SIGNELL KITCHEN REMODEL - JANUARY 2002

Out with the old
kitchen - start time 7:30 a.m.

Baz Whitehead
starts assembly of cabinets Nelson Torrico begins removing cabinets

Nelson completes
wall cabinet removal and marks stud locations for cabinet mounting rail system

Baz keeps
assembling and Nelson completes cabinet removal

Nelson installs
mounting rail and then the first cabinet is installed

Gary Piggot of
Amber Electric runs a new line for the microwave oven

We stage all the
trash then load into the truck and haul away

Nelson installs
last wall cabinet, Baz starts to install doors and customer reviews our progress

Karl Signell seems
pleased with our progress; Chuck McDonald ME checks the level of an
installed base cabinet

Baz & Nelson
team up to install doors

Fillers are
installed and next the microwave goes in

Nelson patches
holes made by the electrician and then installs cabinet handles

It is 4:15 p.m.
and all of the cabinets are installed. A temporary sink is in place and the
kitchen is now ready for the measuring and installation of the granite
countertop. The INEX crew will return to remove the temporary sink and return
after the granite countertop is installed to connect the sink and install the
new faucets.